A modern grey bathroom & a premium kitchen, crafted in 9–10 days.
Prepared for Tumi Mphomane at 12247 Iphenyane Streets, Vosloorus. A clean, stylish and contemporary bathroom renovation paired with a full kitchen installation — managed end to end by 360 Home Enhancers.

Reference: grey tile finish, freestanding tub, black fittings.
A clean, contemporary grey palette.
Plumbing works, full tiling, installation of fittings and finishing — completed with a modern grey tile finish, black tapware and black bathroom accessories.
Finish Selection
Project Duration — 6–7 working days
Plumbing Works
- Preparation of plumbing points
- Adjustments for basin, bath, shower and toilet
- Connection preparation for black tapware & fittings
- Site checks before tiling begins
Tiling Works
- Surface preparation
- Installation of grey wall & floor tiles per approved layout
- Tile alignment, spacing, cutting and edging
- Grouting preparation and curing time
Finishing Works
- Installation of bathroom fittings and accessories
- Taps, shower fittings, toilet and finishing items
- Final checks, cleaning and snagging
Buffer Period
- Two additional days allowed for plumbing adjustments,
- material curing time, site complications or minor snags.
Premium medium kitchen, designed to fit.
The kitchen process begins with a design phase upon acceptance — confirming layout, finishes, measurements, storage, appliance and sink positions, and countertop details before manufacturing.
Inclusions
Project Duration — 3 working days
Installation Start
- Delivery and placement of kitchen units
- Base unit and wall unit installation
- Alignment and fixing of cabinets
Countertop, Sink & Appliance Prep
- Quartz countertop fitting preparation
- Sink installation preparation
- Stove and oven positioning
- Backsplash preparation
Final Installation & Finishing
- Final cabinet adjustments
- Backsplash tiling completion
- Final fittings, silicone, cleaning and snag checks

Reference: matte grey cabinetry, quartz surfaces, minimal hardware.
Kitchen designing commences once the quotation is accepted.
Plumbing material is not included in the quoted amount unless stated otherwise.
Final timelines may be affected by site conditions, material availability, curing times or client changes.
Any work outside the approved quotation will be discussed and quoted separately before proceeding.
Client approval of layout, finishes and design details is required before final kitchen production or installation begins.
“360 Home Enhancers will manage the project professionally to ensure quality workmanship, clean finishes, and a smooth renovation experience.”